1. Enter the password of the electromagnetic flowmeter to enter the menu, and find the column of caliber. For example, the caliber is DN50. At this time, if you want to increase the flow rate, change the caliber DN50 to DN65. Naturally, its flow rate is larger than that of DN50.
2. Another way to adjust the flow, enter the password to enter the menu, find the K coefficient column, for example, the K coefficient is 1.065, if you want the flow to increase, adjust the K coefficient value. the bigger.
3. Before the electromagnetic flowmeter is commissioned, the pipeline and the flowmeter should be thoroughly checked, including the cleaning of the pipeline debris, and the oily medium pipeline does not need to be dried. The inspection before commissioning also includes the inspection of the electrical circuit. First, the connection of the circuit should be tested to ensure that the grounding is reliable before other circuit tests and inspections can be performed to avoid the capacitive effect of the circuit, the storage of electricity, or the measurement power supply. . In addition, insulation resistance and grounding resistance tests are also required.
4. Water commissioning: Whether it is an instrument for measuring aqueous medium suspension liquid or oily medium, before the formal commissioning of the electromagnetic flowmeter, the water commissioning should be carried out by simulating the temperature, pressure, flow rate and other conditions of the actual measurement medium. If an abnormality occurs during the water-passing test, or the parameters are missing, the instrument should be tested individually or sent to the production unit for verification.
5. System investigation and test: After the electromagnetic flowmeter has completed the single function water test, and the preparatory debugging of the control host is completed, the system debugging can be carried out. The oily medium pipeline needs to be dried before passing the measured medium for system operation. When debugging the system, the host should scan the code of each measuring point in advance to ensure that all instrument components are in normal working condition before functional debugging. During functional debugging, the host system will read the parameters of each instrument, test the threshold value alarm, etc., and then write the control data, debug one by one, and send the relevant data to the relevant upper computer for analysis.